Moving Along

Posted on in Construction Alerts
  • Font size: Larger Smaller
  • Subscribe to this entry
  • Print

 

Work is moving along. Some quick updates:

 

 

 

This week


-formed and poured the curb and gutter on the north side of Jefferson (Leavenworth to Jones)

-continued waterline installation work Leavenworth to Hyde
-started forming the roadway for the first half of that block (Leavenworth to Hyde)

-made progress on Leavenworth intersection

 

Next Week (ending April 26th)
-continue forming the roadway Leavenworth to Hyde to mid-block
-continue waterline installation work Leavenworth to Hyde and at the intersections

-work on demo and rebuilding the intersections, including Jones
-Traffic Note: switch traffic on the Jones to Leavenworth block to the south lane pushed to later this month

 

 

Monday's Community Meeting has been rescheduled to the next Monday, April 29th at 10am.